Abstract:
Road projects often experience delays and even construction stops in the middle of
construction. The objectives of this paper is to determine the factors causing delays in
the implementation time of road projects, determine the risk factors that have the most
influence on these projects and provide solutions to reduce or overcome the impact of
delays. This paper was specifically conducted on roads in South Kalimantan, which is
an area with swampy land. Firtsly, distributing questionnaires and interviews to
management staff and construction workers. Data analysis using the Severity Index
method and the risk assessment matrix. The results indicate that, delay in providing
heavy equipment, so must to provide heavy equipment at an earlier time. Damage to
heavy equipment during project implementation, the response is to repair the equipment
as soon as possible or by renting additional equipment. There was a design change
when the project implementation took place, the response was to ask for more time by
the owner. Apply overtime hours to change work schedules when bad weather occurs.