Abstract:
With an area of 98.46 km2 whose territory is
separated by rivers, to increase economic
growth Banjarmasin City has done
infrastructure development in the field of
transportation of roads and bridges are quite
significant. But
in the process of
implementation, there is often a delay in the
bridge construction project. This can lead to
problems within the scope of the project itself.
So it is necessary to do further research to
know the cause of the bridge construction
project delay. This research is conducted
qualitatively and quantitatively. The causative
factors obtained from the literature were
distributed
to
contractors
through
questionnaires to see perceptions of
contractors and concessions. The data of the
questionnaire were analyzed by using validity
test, reliability, and descriptive statistical
analysis with Pearson Moment (Bivariate
Pearson) method assisted by ms. excel to get
the factors causing the delay. Then the delay
factors will be tested through interviews with
stakeholders in the three bridge samples.
Based on the results of data processing
analysis, it can be concluded that the factors
that greatly affect the bridge construction
project delays are analyzed by descriptive
analysis of material arrival delay, material
arrival delay, damage due to negligence of
work, and work that does not comply with
operational standards