The risks involved in construction projects are numerous, but only a few
risks need to be made a priority scale. Therefore, parties in the construction project
need to give priority to important risks that will affect the profitability of the project.
To find out the identification of the dominant risk in the project, it was carried out by
distributing a questionnaire to 23 respondents consisting of 6 correspondents from the
PUPR Office of South Kalimantan Province as the project owner, 12 respondents from
service providers, and 5 respondents from supervisory consultants who were directly
involved in the construction of the new access road project at Syamsudin Noor Airport.
Based on the results of data analysis and validation involving experienced parties and
directly involved in the construction of a new road west access to Syamsudin Noor
Airport, 39 security risks were identified from 9 sources of risk, namely elements of
Politics, Economic, Environment, Finance, Natural, project, Technical, Human and
Safety . Judging from the analysis of the level of risk acceptance, the dominant risks in
this study are unacceptable and undesirable. In terms of the impact of risk on project
delays there are 4 risks (10%) unacceptable and 10 risks (26%) undesirable. In terms
of the impact of risk on finances, there is 1 risk (3%) and 5 risks (13%) undesirable. |