dc.contributor.author |
Gede Sastrawan, I Komang |
|
dc.contributor.author |
Subagyo, Rachmat |
|
dc.date.accessioned |
2023-04-10T00:39:19Z |
|
dc.date.available |
2023-04-10T00:39:19Z |
|
dc.date.issued |
2020 |
|
dc.identifier.issn |
2745-6331 |
|
dc.identifier.uri |
https://repo-dosen.ulm.ac.id//handle/123456789/28195 |
|
dc.description.abstract |
The study aims to determine the heat transfer and performance of cooling tower
Pulang Pisau I Power Plant (2 x 60 MW) by comparing the result data obtained
during commissioning and 2018. Pulang Pisau I Power Plant (2 x 60 MW) is a
power plant using a closed cooling system with the cooling tower. Cooling tower
in a power plant have a very important role, as the main cooling media to keep
the condenser temperature stable. Cooling tower is one of the heat transfer
equipment in a power plant. In Pulang Pisau I Power Plant (2 x 60 MW), cooling
tower performance needs to be examined and analyzed how heat transfer and
efficiency are to get some input to improve / maintain the performance of the
cooling tower. The highest rate of heat transfer from Pulang Pisau - Daya PLTU I
2 x 60 MW cooling tower occurred on December 2nd, 2018 at 06.00 WIB, a load
of 51.0 MW which was 6.883 kW and the lowest occurred on November 24th,
2018 at 15.00 WIB, 14.6 MW which was 2.752 kW. Average efficiency value of
71%. |
en_US |
dc.language.iso |
other |
en_US |
dc.publisher |
Jurnal Tugas Akhir Mahasiswa Rotary |
en_US |
dc.relation.ispartofseries |
2;2 |
|
dc.subject |
Cooling Tower, Analysis, Heat Transfe |
en_US |
dc.title |
ANALISA PERPINDAHAN PANAS COOLING TOWER (INDUCED DRAFT) PLTU I PULANG PISAU (2 x 60 MW) |
en_US |
dc.type |
Other |
en_US |