dc.description.abstract |
This study aims to determine the water supply / discharge system of water
pretreatment station equipment which is then processed for the purpose of
operating a steam power plant. In the distribution process, the reliability of the
equipment and the resulting discharge will be observed whether it is in
accordance with the provisions for the ideal operation or not. The expected
discharge is 518 m3 / h according to the water balance so that the plant can
operate full load (2x66 MW). With this condition, the company is expected to
benefit. In the actual conditions this ideal discharge condition is not achieved so
that the impact of the plant cannot operate full load (2x66 MW). With water
conditions that do not match these expectations, it is feared that the company will
continue to suffer losses. In fact, this study only obtained a maximum discharge
of 402.2 m3 / h. From this figure there is a difference in water debit of 115.8 m3 /
h. Furthermore, this debit shortage must be overcome so that the generator can
meet the maximum full load performance. For long-term steps, standby backup
equipment must be provided in anticipation of the operation. |
en_US |
dc.publisher |
Jurnal SJME Kinematika |
en_US |
dc.relation.ispartofseries |
Volume 4;Nomor 1 |
|
dc.subject |
Water Supply, Water Balance, Maximum Discharge, Standby Backup |
en_US |
dc.title |
Peer Review-Analisa Sistem Suplai Air Produksi dan Air Pendingin Untuk Kehandalan Operasi di PLTU Pulang Pisau (2 x 66 MW) |